Baja+094
Baja
READY PARTS
Vehicle Info
Customer
Andrew Differender
Dealer
Marketing / Sales
VIN
1FD0W5HTXTEC13602
Progress
Ordered
In Shop
Rough In
Systems
Punch List
Ready To Ship
Delivered
Timeline
MilestoneScheduledActual
StartJan 6, 2026Feb 10, 2026 ↑
CompletionMar 24, 2026
Dealer ShipMar 27, 2026
Factory PickupApr 1, 2026
61d overdue
Parts Issue
CUSHIONS, bases are here, top cushions will be ready for pick up 3/31 - (Lolo)

Julio taking evening of 3/30 to tint windows, coming back morning of 3/31 (Justin)
Concern for Delay
-This needs to go back to diversified after completion for undercarriage coating -parts, need eta/tracking from Andrew -this is still on track to deliver wed 4/1 -behind because of electricians being sick